|
The Challenge
The Dounreay PFR contained 1500t of sodium coolant, and as such is a
significant hazard. Although the PFR was carefully designed to be free
draining, during drainage several hold up points resulting in between 20
and 40 tonnes of sodium being left in the reactor.
The Solution
The AMRR Alliance (UKAEA, Sinclair Knight Merz (SKM), Babtie, JGC
Engineering and Alstec ) was formed to solve the problem of removing the
remaining sodium within the reactor. The process designed to solve the
problem was the Water Vapour Nitrogen (WVN) system.
This system allows a controlled reaction to occur between the water
vapour, held in a heated nitrogen carrier, and the sodium. The resulting
reaction creates liquid and gaseous by-products in the form of sodium
hydroxide and hydrogen. The ultimate aim being to use the process on the
sodium pools within the reactor.
The WVN process is an unknown quantity in the nuclear industry and as
such requires extensive proving and development to maintain safety. The
design and modification of the process is continuous and as such new
challenges occur regularly.
The projects for the WVN process are the treatment of the PFR sodium
tank farm, the PFR secondary sodium circuits, various reactor components
termed ‘the sodium inventory’, and the reactor and ancillary equipment.
Before the process is used on the above projects, a series of extensive
testing projects have been carried out at the Janetstown off-site facility
using non-contaminated sodium. This testing phase has provided vast
amounts of data and operational experience to enable future projects to
progress. A second WVN rig has been designed and manufactured to
complete the treatment of the PFR sodium tank farm and sodium inventory.
The testing phase is nearing completion, with all bulk sodium treatment
tests complete. The size of test ranged from 5kg to 1000kg of clean
sodium.
Due to the complex geometry of the reactor vessel interior, testing
involving the cleaning of varying diameter pipework and valves is currently
being undertaken.
Conclusions
The experience and expertise of the Alliance members has proved an
effective team at resolving the challenges faced; the perfect platform to
design, develop, manufacture, operate and analyse the WVN process for
use within the nuclear industry. T3|UK facility has proved to be key in the
gaining of operational experience in controlling the WVN process for future
projects, allowing for the creation and implementing safe systems of work,
such as a permit to work system to enable safe operations.
|